St George Boulevard
Re-construction Updates
6.25.2005 UPDATE:
Western Quality Concrete officials have discovered that it will much
more practical to replace the waterline as they enter into the four
block sections. This will alleviate some major problems at the
intersections as the project proceeds.
And because of the change in the water line installation, full scale
construction has been moved up to July 11th
beginning on 100 West and moving west to 300 West on the Boulevard.
ST. GEORGE BOULEVARD
RECONSTRUCTION SCHEDULE..
The construction on St.
George Boulevard will be completed in eight phases over the course of
400 days, and it is scheduled to start in late July, 2005. The phases
are tentative but are expected to go in the following order:
1.100 West to 300 West
Map
2.300 East to 500 East
Map
3.300 West to Bluff Street
Map
4.100 West to 100 East
Map
5.500 East to 700 East
Map
6.100 East to 300 East
Map
7.700 East to 900 East
Map
8. 900 East to 1100 East
Map
www.stgeorgeboulevard.com
|